The 8.5km contract, M5/2, from Catshill to Rashwood was completed in time for Christmas 1986, in 85 weeks, thus cutting the Contract period by some 28 weeks. This early completion provided three lane motorway on M5 ready for the opening of M42 southern turn which was connected to M5 at Catshill on the 18th March 1987. Work continued throughout the winter of 1985/1986 with the anticipated suspension of earthworks and asphalt laying as determined by weather and temperature; although the use of EVA in the wearing course did facilitate working which otherwise would have been impossible. The Contractor was A Monk & Co.

100,000 tonnes of recycled cement bound granular base (CBGB) and blacktop, taken from superseded sections of the scheme, were incorporated into the new pavement structure as a capping layer on this contract.
The scheme included sixteen existing structures, six overbridges, six underbridges and four culverts. The overbridge spans (two side roads, three farm access and one footbridge) were all too short and the under bridges too narrow to accommodate the proposed widened motorway.
The essence of the design philosophy was the simplicity of structural form, to minimise disruption to traffic and bridge users and also allow the Contractor to carry out key operations during the limited carriageway possessions available.
To achieve these aims the new structures were built alongside the existing which remained in use until the new work was complete. The new overbridges are of steel/concrete composite construction, five being of single-span configuration and one a two-span structure crossing both M5 and M42 slip road. The plate girders with spans up to 49m were manufactured by Fairfield Mabey at their Chepstow Works. Foundations were generally spread footing founded on sandstone at the northern end of the scheme or marl at the southern end, although Upton Warren overbridge was founded on bored cast in-situ piles.
During overnight possessions of the motorway, the new deck girders were lifted into position in the form of braced pairs. These were 'boarded out' to allow the Contractor to continue construction of the new deck the following morning over the live motorway.
Demolition of the existing structures was also carried out during the night-time possessions. The single-span farm overbridges were demolished using controlled explosives, whilst the four-span side road bridges were 'cut' and lowered to the ground on jacks or broken up using machine mounted hydraulic breakers.
Underbridges were generally widened symmetrically using a similar form of construction to the existing. Some of the existing decks were strengthened by over stabbing and in two cases completely replaced. As with the overbridges, foundations were generally spread footings with the exception of the two most southerly bridges where bored cast in-situ piles were employed. Although at face value less spectacular than the overbridge structures the design and construction of the underbridges did pose a greater challenge and great care was taken to ensure the new extensions did not impart additional load to the existing structures.
In addition to replacement and extension of the existing structures, three new sign gantries were required to carry advanced direction signing for the proposed M42 junction at Catshill. These structures have been fabricated to standard Department of Transport designs.